Continuous report I
Situation at January 2008:
DTL/DML based Mission Control System Demonstrator
Purpose of this new follow up GSTP/PECS activity is to verify the new EGOS Data Transfer and Data Management libraries within a mission control system. The telemetry reception and telemetry distribution chain of SCOS-2000 will be re-engineered adopting these libraries.
The project kick-off was in December 2007, expected end of project is in September 2009.
This project is also performed in cooperation with Siemens Austria as the prime contractor within the GSTP program, and ANF Data as a subcontractor within the PECS program.